Play Live Radio
Next Up:
0:00
0:00
0:00 0:00
Available On Air Stations
Supported by

Faraday Future Behind On Contractor Payments

Automotive News reports Faraday Future is behind on payments to construction firms contracted to build its facility at the Apex Industrial Park in North Las Vegas.

Contractor AECOM says it is owed roughly $37 million so far and threatened a work stoppage.

In a joint statement to Automotive News, both Faraday and AECOM said the factory will still be built as planned.

Casey Morell is the coordinating producer of Nevada Public Radio's flagship broadcast State of Nevada and one of the station's midday newscast announcers. (He's also been interviewed by Jimmy Fallon, whatever that's worth.)